An under-construction apartment purchase is a commitment to documents, specifications and future performance. Verify each material promise before paying a booking amount.
Approved plans and registration
Request the sanctioned plan, approval references and the project’s RERA registration or documented exemption basis. Compare the marketed apartment type with the approved plan. MoHUA’s RERA materials focus buyer attention on sanctioned plans, apartment types and carpet area, proposed agreements, completion period and project progress updates.
Carpet area, UDS and total cost
Match the dimensioned plan to the stated carpet area. Ask how balconies, walls and common areas are treated, and confirm UDS in the agreement. Build a total-cost sheet including parking, taxes, registration, utilities, maintenance deposits and fit-out.
Payment milestones and the agreement
Tie payments to clearly defined construction milestones and evidence. Review cancellation, delay, interest, substitution, specification-change, possession and defect terms with an independent lawyer. RERA requires 70% of amounts realised for a project to be placed in a project-specific separate account and used for land and construction costs, with withdrawals linked to certified progress; this safeguard does not replace project-specific diligence. See the Real Estate (Regulation and Development) Act.
Ready to turn the checklist into a project-specific conversation?
Specifications and progress evidence
Ask for a signed specification schedule and the substitution process. Progress evidence should be dated and should correspond to the block, floor or work package relevant to the payment claim. Site photographs are useful when combined with an engineer’s or architect’s certified milestone.
Possession and handover
Record the contractual possession period, grace provisions, completion documentation, snagging process, meter status, warranties and defect response. Do not infer a completion date from phrases such as “construction in full swing.”
Drainage and monsoon checklist
At the exact site, inspect street elevation, drain continuity and outlet, basement or stilt level, ramp crest, pump and backup arrangements, and nearby residents’ experience of past waterlogging. GCC explains Chennai’s general stagnation risk and records stormwater work in Valasaravakkam; it does not remove the need for site-level checks.
For Chandra Residences, request the current approved plans, carpet-area schedule, UDS, price sheet, payment plan, specifications, registration/approval details, possession wording and dated progress evidence before booking.